German company Voith Hydro has been awarded a contract by Endesa Chile for the supply, installation, and commissioning of electromechanical equipment for the Los Cóndores hydropower plant, which is under construction in the mountainous area of the Maule Region.

The plant comprises two Pelton vertical axis generators, installed in an underground machine room, which have an installed capacity of approximately 150MW.

Estimated to have a plant factor of 48% and an average annual generation of 642GWh, the Los Cóndores project is a part of Endesa Chile, which aims to develop the country’s electricity, providing clean, renewable, and low operating cost energy.

Under the contract, Voith Hydro will be responsible for the electromechanical development, equipment engineering, manufacturing, installation, supervision, commissioning services and project management.

The electromechanical development scope includes two Pelton turbines, two generators, plant and product engineering, manufacturing, erection, supervision, commissioning and project management services.

Voith will manufacture the project’s key components in São Paulo, Brazil.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The plant, which uses water from the Laguna del Maule reservoir through a 12km adduction tunnel, will have less environmental impact on the scenery, soil, vegetation, and fauna in the area.

The project’s all civil works including among others, intake, adduction tunnel, pressure pique, underground powerhouse and discharge channel will be completed in about five years and is slated to commence commercial operations in the fourth quarter of 2018.