Merengue II Wind Farm is a 49.5MW onshore wind power project. It is planned in Extremadura, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. The project construction is likely to commence in 2022 and is expected to enter into commercial operation in 2023. Buy the profile here.
Description
The project is being developed and currently owned by Naturgy Renovables. The company has a stake of 100%.
The project is expected to generate 128,000MWh electricity to offset 81,500t of carbon dioxide emissions (CO2) a year.
The Tubular Steel structure to be installed at the project site are expected to be 132m high.
Development status
The project construction is expected to commence from 2022. Subsequent to that it will enter into commercial operation by 2023.
Contractors involved
Nordex will be the turbine supplier for the wind power project. The company is expected to provide 11 units of N155/4.X turbines, each with 4.5MW nameplate capacity.
For more details on Merengue II Wind Farm, buy the profile here.
About Naturgy Renovables
Naturgy Renovables SL (Naturgy Renovables) generates, transmits, and distributes electricity through solar energy. Naturgy Renovables headquartered in Spain.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.