Liujiaxia is a 1,350MW hydro power project. It is located on Yellow river/basin in Gansu, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1958 and subsequently entered into commercial operation in 1969. Buy the profile here.
Description
The project is developed and owned by State Grid Gansu Electric Power.
Liujiaxia is a reservoir based project. The hydro reservoir capacity is 5,700 million cubic meter. Liujiaxia underwent through rehabilitation & modernization during 1994, 1998-2000, 2001-2002. The project generated 5,700 GWh of electricity.
The hydro power project consists of 2 turbines, each with 225MW nameplate capacity.
Development status
The project construction commenced in 1958 and subsequently entered into commercial operation in 1969.
Power purchase agreement
The power generated from the project is sold to State Grid Corporation of China under a power purchase agreement.
Contractors involved
Harbin Electric Machinery was selected as the turbine supplier for the hydro power project. The company provided 1 turbine with 225MW nameplate capacity.
Harbin Electric Machinery was selected as the turbine supplier for the hydro power project. The company provided 1 turbine with 300MW nameplate capacity.
For more details on Liujiaxia, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.