Ciner Kazan Soda Combined Cycle Cogeneration Plant is a 379MW gas fired power project. It is located in Ankara, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in January 2018. Buy the profile here.
Description
The project is developed and owned by Kazan Soda Elektrik Uretim. The company has a stake of 100%.
It is a CCGT with Cogen power plant.
Development status
The project got commissioned in January 2018.
Contractors involved
China Tianchen Engineering was selected to render engineering procurement construction services for the gas fired power project.
Siemens Energy was selected as the turbine supplier for the Gas fired project. The Gas fired project consists of 1 gas turbine.
Siemens Energy was selected as the turbine supplier for the Gas fired project. The Gas fired project consists of 1 steam turbine.
Siemens Energy supplied SGen-1200A, SGen-100A electric generator for the project.
For more details on Ciner Kazan Soda Combined Cycle Cogeneration Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.