Apex Solar PV Park is a 105MW solar PV power project. It is planned in Montana, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. Post completion of the construction, the project is expected to get commissioned in 2023. Buy the profile here.
Description
The project is being developed and currently owned by Clenera. The company has a stake of 100%.
Apex Solar PV Park is a ground-mounted solar project which is planned over 639 acres.
The project is expected to supply enough clean energy to power 30,000 households.
Development status
Post completion of the construction, the project is expected to get commissioned in 2023.
Power purchase agreement
The power generated from the project will be sold to NorthWestern under a power purchase agreement for a period of 25 years. The offtake capacity is expected to be 80MW.
Contractors involved
Waaree Energies will be the supplier of the PV modules for the solar power project. The company is expected to provide 160,000 modules each with 590W of nameplate capacity.
For more details on Apex Solar PV Park, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.