Global transmission capacity was estimated to have reached 19,883,744MVA by the end of 2021 and is forecasted to grow to 27,052,399MVA by 2027. Mexico had 191,138MVA of capacity in 2021 and this is expected to rise to 207,903MVA by 2027. Listed below are the five largest transmission projects by capacity in Mexico, according to GlobalData’s power database. GlobalData uses proprietary data and analytics to provide a complete picture of the global transmission segment. Buy the latest transmission substation project profiles here.
1. Tecpatan HVDC Substation
Tecpatan HVDC Substation is a 500/400kV substation located at Tecpatan, Chiapas, Mexico. The substation is planned and is expected to be commissioned in 2025. The Tecpatan HVDC Substation will be operated by Comision Federal de Electricidad.
The designed voltage level of the substation is 500/400kV and the operating voltage level is 500/400kV. The step in voltage of the project is 500kV and the step out voltage is 400kV. Upon completion, the substation will be able to operate at 1950MVA.
Tecpatan HVDC Substation is owned by Comision Federal de Electricidad. Buy the profile here.
2. Bacum Bancos III Substation
Bacum Bancos III Substation is a 400/230/115kV substation located at Bacum Bancos, Sonora, Mexico. The substation is planned and is expected to be commissioned in 2024. The Bacum Bancos III Substation will be operated by Comision Federal de Electricidad.
The designed voltage level of the substation is 400/230/115kV and the operating voltage level is 400/230/115kV. The step in voltage of the project is 400kV and the step out voltage is 115kV. Upon completion, the substation will be able to operate at 875MVA.
Bacum Bancos III Substation is owned by Comision Federal de Electricidad. Buy the profile here.
3. Guerreno Substation
Guerreno Substation is a 400/138kV substation located at Guerreno, Guerreno, Mexico. The substation is planned and is expected to be commissioned in 2024. The Guerreno Substation will be operated by Comision Federal de Electricidad.
The designed voltage level of the substation is 400/138kV and the operating voltage level is 400/138kV. The step in voltage of the project is 400kV and the step out voltage is 138kV. Upon completion, the substation will be able to operate at 375MVA.
Guerreno Substation is owned by Comision Federal de Electricidad. Buy the profile here.
4. Moctezuma Substation – New – 400/230 kV
Moctezuma Substation – New – 400/230 kV is a 400/230kV substation located at Moctezuma, Sonora, Mexico. The substation is proposed and is expected to be commissioned in 2026. The Moctezuma Substation – New – 400/230 kV will be operated by Comision Federal de Electricidad.
The designed voltage level of the substation is 400/230kV and the operating voltage level is 400/230kV. The step in voltage of the project is 400kV and the step out voltage is 230kV. Upon completion, the substation will be able to operate at 375MVA.
Moctezuma Substation – New – 400/230 kV is owned by Comision Federal de Electricidad. Buy the profile here.
5. Puerto Altamira Substation
Puerto Altamira Substation is a 400kV substation located at Puerto Altamira, Tamaulipas, Mexico. The substation is planned and is expected to be commissioned in 2024. The Puerto Altamira Substation will be operated by Comision Federal de Electricidad.
The designed voltage level of the substation is 400kV and the operating voltage level is 400kV. The step in voltage of the project is 400kV. Upon completion, the substation will be able to operate at 375MVA.
Puerto Altamira Substation is owned by Comision Federal de Electricidad. Buy the profile here.
For more details on the latest transmission substation projects, buy the project profiles here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.