Global transmission capacity was estimated to have reached 19,883,744MVA by the end of 2021 and is forecasted to grow to 27,052,399MVA by 2027. Malaysia had 146,763MVA of capacity in 2021 and this is expected to rise to 166,150MVA by 2027. Listed below are the five largest transmission projects by capacity in Malaysia, according to GlobalData’s power database. GlobalData uses proprietary data and analytics to provide a complete picture of the global transmission segment. Buy the latest transmission substation project profiles here.
1. Baleh Substation
Baleh Substation is a 500kV substation located at Baleh Hydro Power Plant, Sarawak, Malaysia. The substation is planned and is expected to be commissioned in 2023. The Baleh Substation will be operated by Sarawak Energy Bhd.
The designed voltage level of the substation is 500kV and the operating voltage level is 500kV. The step in voltage of the project is 500kV.
Baleh Substation is owned by Sarawak Energy Bhd. Buy the profile here.
2. Bukit Unggul Substation
Bukit Unggul Substation is a 500/275kV substation located at Bukit Unggul, Selangor, Malaysia. The substation is under construction and is expected to be commissioned in 2023. The Bukit Unggul Substation will be operated by Tenaga Nasional Bhd.
The designed voltage level of the substation is 500/275kV and the operating voltage level is 500/275kV. The step in voltage of the project is 500kV and the step out voltage is 275kV.
Bukit Unggul Substation is owned by Tenaga Nasional Bhd. Buy the profile here.
3. Junjung Kedah Substation
Junjung Kedah Substation is a 500/275kV substation located at Junjung Kedah, Kedah, Malaysia. The substation is under construction and is expected to be commissioned in 2023. The Junjung Kedah Substation will be operated by Tenaga Nasional Bhd.
The designed voltage level of the substation is 500/275kV and the operating voltage level is 500/275kV. The step in voltage of the project is 500kV and the step out voltage is 275kV. Upon completion, the substation will be able to operate at 3150MVA.
Junjung Kedah Substation is owned by Tenaga Nasional Bhd. Buy the profile here.
4. Tondong Substation
Tondong Substation is a 500kV substation located at Tondong, Sarawak, Malaysia. The substation is under construction and is expected to be commissioned in 2023. The Tondong Substation will be operated by Sarawak Energy Bhd.
The designed voltage level of the substation is 500kV and the operating voltage level is 500kV. The step in voltage of the project is 500kV.
Tondong Substation is owned by Sarawak Energy Bhd. Buy the profile here.
5. Tondong Substation – New
Tondong Substation – New is a 500/275/132kV substation located at Tondong, Sarawak, Malaysia. The substation is under construction and is expected to be commissioned in 2023. The Tondong Substation – New will be operated by Sarawak Energy Bhd.
The designed voltage level of the substation is 500/275/132kV and the operating voltage level is 500/275/132kV. The step in voltage of the project is 500kV and the step out voltage is 132kV.
Tondong Substation – New is owned by Sarawak Energy Bhd. Buy the profile here.
For more details on the latest transmission substation projects, buy the project profiles here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.